Project Updates

State Pier East Side

timeline

  • March 30, 2021

    Evidentiary Hearing portion of the CTDEEP Public Hearing will be held. Evidentiary Hearing will continue on March 31, April 6, and April 7, as needed. 

  • March 23, 2021

    Public Comment Session portion of the CTDEEP Public Hearing is held

  • February 12, 2021

    CTDOT commences on-site remediation

  • DECEMBER 21, 2020

    Final Remedial Action Plan (RAP) is submitted to CTDEEP

  • DECEMBER 18, 2020

    Kiewit Infrastructure Co. is selected as the Construction Manager At-Risk

  • DECEMBER 16, 2020

    CTDEEP Public Notice is released

  • October 30, 2020

    Revised JPA (Revision 2) is submitted to CTDEEP and USACE documenting revised dredge footprints

  • October 21, 2020

    90% Design Documents are submitted

  • October 7, 2020

    Phase III Environmental Site Assessment is completed

  • September 22, 2020

    Request for Proposal (RFP) for a CMR firm is released

  • August 4, 2020

    USACE Public Notice is released

  • July 28, 2020

    60% Design Documents are submitted

  • July 21, 2020

    Request for Qualifications (RFQ) for a Construction Manager At-Risk (CMR) firm is released

  • June 1, 2020

    30% Design Documents are submitted

  • May 8, 2020

    Revised JPA (Revision 1) is submitted to CTDEEP and USACE documenting revised Installation Vessel berthing configuration

  • April 27, 2020

    AECOM is conditionally selected as the Construction Administrator

  • April 7, 2020

    Construction Stormwater General Permit authorization is issued by CTDEEP

  • January 9, 2020

    Construction Stormwater General Permit application submitted to CTDEEP

  • November 1, 2019

    USACE issues CT GP Authorization under GP 2

  • October 7, 2019

    CTDEEP issues Certificate of Permission (COP)

  • September 11, 2019

    Application for Certificate of Permission (COP) and Connecticut General Permit (CT GP) authorization are submitted for select Phase 1 activities (oversheeting the Northeast Bulkhead, demolition of the Mooring Dolphins, Northeast Annex and related activities)

  • May 6, 2019

    Joint Permit Application (JPA) is submitted to Connecticut Dept. of Energy & Environmental Protection (CTDEEP) and U.S. Army Corps of Engineers (USACE)

PHOTOS