Project Updates

State Pier East Side

timeline

  • October 30, 2020

    Revised JPA (Revision 2) is submitted to CTDEEP and USACE documenting revised dredge footprints

  • October 21, 2020

    90% Design Documents are submitted

  • October 7, 2020

    Phase III Environmental Site Assessment is completed

  • September 22, 2020

    Request for Proposal (RFP) for a CMR firm is released

  • July 28, 2020

    60% Design Documents are submitted

  • July 21, 2020

    Request for Qualifications (RFQ) for a Construction Manager At-Risk (CMR) firm is released

  • June 1, 2020

    30% Design Documents are submitted

  • May 8, 2020

    Revised JPA is submitted to CTDEEP and USACE documenting revised Installation Vessel berthing configuration

  • April 27, 2020

    AECOM is conditionally selected as the Construction Administrator

  • April 7, 2020

    Construction Stormwater General Permit authorization is issued by CT DEEP

  • January 9, 2020

    Construction Stormwater General Permit application submitted to CT DEEP

  • November 1, 2019

    USACE issues CT GP Authorization under GP 2

  • October 7, 2019

    CTDEEP issues Certificate of Permission (COP)

  • September 11, 2019

    Application for Certificate of Permission (COP) and Connecticut General Permit (CT GP) authorization submitted for select Phase 1 activities (oversheeting the Northeast Bulkhead, demolition of the Mooring Dolphins, Northeast Annex and related activities).

  • May 6, 2019

    Joint Permit Application (JPA) is submitted to Connecticut Dept. of Energy & Environmental Protection (CTDEEP) and U.S. Army Corps of Engineers (USACE)