Project Updates
timeline
-
JUNE 20, 2024
Wind components staged on site.
-
JUNE 20, 2024
Wind turbine tower sections staged on site.
-
JUNE 5, 2024
Vessel berthed on State Pier.
-
JUNE 3, 2024
Blades being offloaded for next wind project.
-
MAY 3, 2024
Aerial view of final completion Central Wharf, with vessel at berth.
-
MAY 3, 2024
Aerial view of final completion Central Wharf.
-
MAY 3, 2024
South Wall completion.
-
APRIL 26, 2024
State Pier mooring bollard pad.
-
APRIL 25, 2024
Final South Wall pile cap pour.
-
APRIL 25, 2024
Aerial view of final South Wall pile cap pour.
-
APRIL 25, 2024
CVRR Pier West Return.
-
APRIL 8, 2024
State Pier mooring bollard pad form.
-
MARCH 22, 2024
West Return Finishing.
-
MARCH 22, 2024
Outfall #4 Cofferdam.
-
MARCH 22, 2024
Completed Central Wharf.
-
MARCH 19, 2024
Outfall #4 pipe and TideFlex valve.
-
MARCH 18, 2024
Outfall #4 Cofferdam.
-
MARCH 8, 2024
Hydrodynamic Separator - Aluminum Swirl Chamber.
-
MARCH 4, 2024
Reinforcing steel at South Wall pile cap.
-
MARCH 4, 2024
CVRR Pier west return closure.
-
MARCH 1, 2024
Outfall #4 cofferdam.
-
FEBRUARY 19, 2024
Drilling bit.
-
FEBRUARY 19, 2024
CVRR Pier West Return tremie pour.
-
FEBRUARY 8, 2024
Finishing South Wall.
-
JANUARY 29, 2024
CVRR West Wall.
-
JANUARY 29, 2024
Super tugs.
-
JANUARY 19, 2024
South Wall gap closure.
-
JANUARY 12, 2024
Coil rod repair mockups.
-
JANUARY 10, 2024
Overall view of ongoing work.
-
JANUARY 10, 2024
CVRR West Return.
-
DECEMBER 31, 2023
Mooring bollard pad formwork.
-
DECEMBER 31, 2023
Central Wharf area turned over to Operations.
-
DECEMBER 5, 2023
Wind turbine nacelles staged for offloading.
-
DECEMBER 5, 2023
Wind turbine tower sections staged for offloading.
-
NOVEMBER 28, 2023
State Pier cold ironing (shore power) electrical pad construction.
-
NOVEMBER 28, 2023
State Pier Relieving Platform final pour preparation.
-
OCTOBER 27, 2023
Outfall #4 mock-up.
-
OCTOBER 23, 2023
Wind turbine blades being offloaded to barge.
-
SEPTEMBER 30, 2023
Ongoing construction in foreground, area turned over to Operations in background.
-
SEPTEMBER 20, 2023
Placement of DGA on last portion of State Pier Relieving Platform.
-
SEPTEMBER 20, 2023
Finishing South Wall.
-
SEPTEMBER 1, 2023
Last section of State Pier Relieving Platform.
-
SEPTEMBER 1, 2023
Wind turbine blades on finished Central Wharf.
-
AUGUST 21, 2023
Delivered wind turbine nacelles.
-
AUGUST 16, 2023
Delivery of wind turbine blades.
-
JULY 7, 2023
Wind tower sections.
-
JUNE 16, 2023
View from ferry Susan Ann.
-
JUNE 16, 2023
State Pier Relieving Platform – first concrete pour in background.
-
JUNE 9, 2023
Progress at the South Wall – fill waiting for placement.
-
JUNE 1, 2023
South Wall progress – final fill on left, combi-wall on right.
-
JUNE 1, 2023
Central Wharf progress including final fill, South Wall and State Pier Relieving Platform.
-
MAY 24, 2023
Portion of State Pier Relieving Platform ready for first concrete pour.
-
MAY 19, 2023
State Pier Relieving Platform Steel Reinforcement.
-
MAY 19, 2023
Filling the “Wedge” at South Wall.
-
MAY 12, 2023
Electrical Pad.
-
MAY 5, 2023
South Wall with Tie Rods.
-
MAY 2, 2023
Storm Drainage Installation.
-
APRIL 21, 2023
Finished surface in foreground; continuing work in background.
-
APRIL 14, 2023
South Wall anchor pile.
-
APRIL 5, 2023
South Wall tie-rods.
-
MARCH 27, 2023
Heavy-duty Mooring Bollards at Northeast Annex.
-
MARCH 27, 2023
Electrical Equipment ready for installation.
-
MARCH 22, 2023
Trench drain sloped bottom pour.
-
MARCH 20, 2023
South Wall anchor rods preparation.
-
MARCH 16, 2023
State Pier Relieving Platform Pile Bents 1 & 2.
-
MARCH 10, 2023
Northeast Annex and Bulkhead at Delivery Berth.
-
MARCH 3, 2023
Electrical equipment pad foundation walls.
-
MARCH 1, 2023
Downhole drill for removing obstructions to piles.
-
FEBRUARY 20, 2023
Mooring Bollard at Northeast Annex.
-
FEBRUARY 15, 2023
Dense Graded Aggregate placement and compaction.
-
FEBRUARY 13, 2023
Northeast Annex ready for installation of anchor rods.
-
FEBRUARY 8, 2023
Dredging at Delivery Berth.
-
FEBRUARY 8, 2023
Placement of riprap slope at site entrance road.
-
FEBRUARY 3, 2023
High Mast Light Pole foundation.
-
JANUARY 30, 2023
Electrical conduit into site.
-
JANUARY 20, 2023
Placement of South Wall anchor piles reinforcement.
-
JANUARY 18, 2023
Setting up falsework and formwork for the State Pier Relieving Platform.
-
JANUARY 18, 2023
Aerial view of Outfall #1 construction.
-
JANUARY 7, 2023
Installation Berth Heavy-lift Platform – falsework installation in foreground.
-
JANUARY 7, 2023
Northeast Annex.
-
JANUARY 7, 2023
Installing drainage manholes and pipes.
-
DECEMBER 29, 2022
Battered anchor H-piles at South Wall.
-
DECEMBER 15, 2022
Storm water treatment system at Outfall 1.
-
DECEMBER 9, 2022
Dredging the turning basin
-
NOVEMBER 22, 2022
Installing drainage manholes and pipes.
-
NOVEMBER 11, 2022
Excavation trench box.
-
NOVEMBER 10, 2022
Placing and rolling dense graded crushed stone.
-
OCTOBER 28, 2022
Drainage Outfall 3 with Duckbill.
-
OCTOBER 28, 2022
Disabled scow Eddie Carroll.
-
OCTOBER 24, 2022
Dredging the Turning Basin.
-
OCTOBER 19, 2022
Installation Berth Toe Wall Template.
-
OCTOBER 19, 2022
Delivery Berth Heavy-Lift Platform
-
OCTOBER 6, 2022
Aerial site view looking south.
-
OCTOBER 3, 2022
Drainage system installation.
-
SEPTEMBER 30, 2022
Steel placement at NE Annex combi-wall.
-
SEPTEMBER 21, 2022
NE Annex Mooring Bollards.
-
SEPTEMBER 21, 2022
Delivery Berth Heavy Lift Platform and Bulkhead.
-
SEPTEMBER 12, 2022
Storm drainage excavation dewatering.
-
SEPTEMBER 9, 2022
Storm drain installation, Central Wharf.
-
SEPTEMBER 7, 2022
Delivery Berth reinforcing steel assembly.
-
SEPTEMBER 7, 2022
Aerial view of site looking south.
-
AUGUST 29, 2022
Removed original timber piles.
-
AUGUST 23, 2022
Excavation for removal of original timber piles.
-
AUGUST 23, 2022
Dewatering treatment flocculation tank.
-
AUGUST 23, 2022
Dewatering treatment equipment.
-
AUGUST 22, 2022
Battered H-Piles at NE Annex; storm treatment system in background.
-
AUGUST 18, 2022
Dewatering excavation for storm manhole installation.
-
AUGUST 10, 2022
Installation of Stormwater Treatment System at NE Annex
-
AUGUST 9, 2022
Temporary sheeting at State Pier Heavy-Lift Platform
-
AUGUST 2, 2022
Demolition of State Pier deck at Heavy-Lift Platform
-
AUGUST 2, 2022
Placement of reinforcing steel at Delivery Berth Heavy-Lift Platform
-
JULY 27, 2022
Placing temporary sheeting in State Pier Heavy-lift Platform area
-
JULY 21, 2022
Breaking obstruction in South combi-wall using an H-pile
-
JULY 21, 2022
Removed concrete that was obstructing to State Pier pile driving
-
JULY 19, 2022
Concrete pour of Delivery Berth Heavy-lift Platform
-
JULY 22, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
JULY 11, 2022
Electrical ducts on CVRR Pier
-
JULY 11, 2022
48-inch segmental casing and drill tools
-
JULY 11, 2022
New turbidity curtain deployment
-
JULY 5, 2022
Completing Central Wharf Infill
-
JUNE 16, 2022
Delivery Berth Heavy-lift Pad progress
-
JUNE 10, 2022
Organic silt removed from area beneath Installation Berth Heavy-lift Platform
-
JUNE 10, 2022
Restoration of Retaining Wall adjacent to Delivery Berth
-
JUNE 10, 2022
Demolition of Obstructions at Installation Berth Heavy-lift Platform
-
JUNE 3, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
MAY 26, 2022
Delivery Berth Heavy-lift Platform Backfilling
-
MAY 26, 2022
Installation Berth Heavy-lift Platform Piles
-
MAY 25, 2022
Removal of Obstructions from install Heavy-lift Platform
-
MAY 20, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
MAY 19, 2022
Delivery Berth Heavy-lift Platform reinforcing steel and formwork.
-
MAY 16, 2022
Storm Drainage Installation - Drainage Area 3
-
MAY 13, 2022
South Wall H-Pile Berm
-
MAY 13, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
MAY 12, 2022
Central Wharf Infill
-
MAY 12, 2022
Central Wharf Infilling
-
MAY 11, 2022
Project team representing AECOM (CA), Kiewit (CM) & CPA
-
MAY 11, 2022
Alternate vibro-compaction method for shallow fill
-
MAY 10, 2022
Delivery Berth Combi-wall concrete pour
-
MAY 6, 2022
South Combi-wall Template
-
MAY 6, 2022
Delivery Berth Relieving Platform pile cages
-
MAY 6, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
MAY 2, 2022
Riprap and debris removed from east slope State Pier.
-
MAY 2, 2022
Demolition of East Deck State Pier U-beam.
-
APRIL 27, 2022
Delivery Berth Combi-wall cap formwork.
-
APRIL 27, 2022
Delivery Berth Combi-wall pile pour.
-
APRIL 15, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
APRIL 14, 2022
Delivery Berth Relieving Platform preparation for rebar replacement.
-
APRIL 12, 2022
Delivery Berth combi-wall concrete plug pour.
-
APRIL 8, 2022
Removal of vintage bollards from CVRR Pier.
-
APRIL 8, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
APRIL 5, 2022
Delivery Berth Relieving Platform welding shear rings to piles.
-
MARCH 31, 2022
Removal of obstructions at South Wall anchor piles.
-
MARCH 31, 2022
Demolition of west deck of State Pier.
-
MARCH 29, 2022
Delivery Berth Relieving Platform preparation for rebar cages.
-
MARCH 29, 2022
Removal of portion of east deck of State Pier.
-
MARCH 18, 2022
Aerial view of State Pier west deck demolition.
-
MARCH 18, 2022
Aerial view of stockpile on CVRR Pier. South combi-wall in background.
-
MARCH 18, 2022
Aerial view of State Pier east deck demolition.
-
MARCH 14, 2022
Processing onsite material for Central Wharf infill.
-
MARCH 14, 2022
Removing obstructions at South Wall.
-
MARCH 14, 2022
Steel rebar cages for Delivery Berth Relieving Platform.
-
MARCH 7, 2022
Recycling of steel from demolition of State Pier west deck
-
MARCH 7, 2022
Removal of portion of east deck State Pier
-
MARCH 4, 2022
Vibro-compaction crane
-
MARCH 4, 2022
Processing onsite material for central wharf infill
-
MARCH 4, 2022
Left - Central Wharf infill; Right - Demolition of west desk State Pier
-
MARCH 4, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
MARCH 4, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
FEBRUARY 24, 2022
South Wall Combi-wall at CVRR Pier
-
FEBRUARY 24, 2022
Northeast Annex Combi-wall
-
FEBRUARY 21, 2022
Central Wharf Infilling
-
FEBURARY 18, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
FEBRUARY 16, 2022
Combi-wall cut to height at Delivery Berth
-
FEBRUARY 11, 2022
Installation of combi-wall at south end of CVRR Pier
-
FEBRUARY 2, 2022
Demolition of State Pier West Deck (left) and Fill Placement in the Central Wharf (right)
-
JANUARY 24, 2022
Placement of moguls in the Central Wharf
-
JANUARY 21, 2022
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
JANUARY 20, 2022
Demolition of the Sstate Pier West Deck
-
JANUARY 13, 2022
Commencement of dredging organic silt in central wharf.
-
JANUARY 6, 2022
Delivery Berth Relieving Platform and combi-wall progress.
-
DECEMBER 20, 2021
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
DECEMBER 16, 2021
USACE issues Department of the Army Permit No. NAE-2018-02161. All construction activities are now fully permitted.
-
NOVEMBER 9, 2021
2nd ship unloading pipe piles.
-
NOVEMBER 8, 2021
New dashboard posted. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
NOVEMBER 5, 2021
Pile Dynamic Analysis (PDA) test.
-
OCTOBER 28, 2021
Progress on Delivery Berth Relieving Platform and Combi-wall.
-
OCTOBER 25, 2021
New dashboard posted; The Authority launched a new Dashboard feature to provide the public with a greater insight into the construction activities taking place. The Dashboard will be updated regularly. For previous dashboards, please see "Archived Dashboards" in the Documents Section.
-
OCTOBER 19, 2021
Delivery Berth Combi-wall installation.
-
OCTOBER 14, 2021
Combi-wall installation - Delivery Berth
-
OCTOBER 7, 2021
Piles - Delivery Berth
-
SEPTEMBER 30, 2021
Selecting piles - Delivery Berth
-
SEPTEMBER 24, 2021
Assembly of the pile template
-
SEPTEMBER 22, 2021
Delivery Berth pile installation
-
SEPTEMBER 20, 2021
Pile driving commences at Delivery Birth
-
SEPTEMBER 8, 2021
Staging piles at the Delivery Berth
-
AUGUST 30, 2021
First shipment of pipe piles arrives.
-
AUGUST 25, 2021
Aerial photo view south.
-
AUGUST 18, 2021
CT DEEP License - SDF, TW & 401 WQC received. See State/Federal Documents in the Documents section for PDF.
-
AUGUST 12, 2021
Aerial photo view southeast.
-
AUGUST 2, 2021
Assembling the crane for the Delivery Berth Relieving Platform.
-
JULY 23, 2021
Grading and compacting the soil stockpile on the CVRR Pier.
-
JULY 20, 2021
Aerial photo view southwest.
-
JULY 19, 2021
Northeast Quay Slab Demo.
-
JULY 14, 2021
Stockpiling on the CVRR Pier.
-
JULY 6, 2021
Pre-construction activities and mobilization of crews to perform the mooring dolphin demolition and Northeast Heavy-Lift Platform construction is underway with on-site activities scheduled for the coming weeks
-
JULY 6, 2021
Site clearing of the railroad parcel has commenced with utility excavation planned for mid to late July.
-
JULY 6, 2021
Demolition of existing administration building and southern warehouse buiding (the northern warehouse will remain) together with associated utilities.
-
JULY 6, 2021
Excavation of the earth hill with stockpiling of the soil at the CVRR pier for subsequent placement within the Central Wharf.
-
JULY 2, 2021
Demolition of existing administration building and southern warehouse buiding (the northern warehouse will remain) together with associated utilities.
-
JULY 1, 2021
Excavation of the earth hill with stockpiling of the soil at the CVRR pier for subsequent placement within the Central Wharf.
-
JUNE 29, 2021
Bid Package 036.OHCS.01 On-Site Medical Services is awarded to First Care Connecticut LLC of New Hyde Park, NY. The contracted price for this package is $402,251.75.
-
JUNE 29, 2021
Bid Package 018.SC.13 Furnish & Install Rebar is awarded to Alvarez Industries LLC of Orange, CT. The contracted price for this package is $7,171,545.
-
JUNE 29, 2021
Bid Package 026.SC.18 Electrical Demolition and Install is awarded to Kiewit Infrastructure of Woodcliff Lake, NJ. The contracted price for this package is $6,642,140.
-
JUNE 16, 2021
Demolition of Warehouse 1 and Maintenance Shops.
-
JUNE 15, 2021
Bid Package 033.PA.01 Temporary Guard Booth is awarded to Eagle Leasing Company of Orange, CT. The contracted price for this package is $12,826.
-
JUNE 15, 2021
Bid Package 020.SC.15 State Pier Relieving Platform is awarded to JT Cleary Inc. of Flushing, NY. The contracted price for this package is $22,929,618.
-
JUNE 15, 2021
Bid Package 006.IWO.02 Janitorial Cleaning is awarded to Uniquely Cleaning LLP of Naugatauk, CT. The contracted price for this package is $216,339.
-
MAY 21, 2021
Bid Package 007.SC.04 Site Civil & Drainage is awarded to Kiewit Infrastructure Co. of Woodcliff Lake, NJ. The contracted price for this package is $14,690,000.
-
MAY 21, 2021
Bid Package 015.IWO.05 Street Sweeping is awarded to Northeast Landscaping & Tree Services Inc. of Westerly, RI. The contracted price for this package is $210,180.
-
MAY 21, 2021
Bid Package 009.SC.10 Temporary and Permanent Fence is awarded to P&C Fence of Bridgeport, CT. The contracted price for this package is $250,691.
-
MAY 21, 2021
Bid Package 017.SC.12 Northeast Bulkhead Relieving Platform is awarded to ECD NY, Inc. of Queens, NY. The contracted price for this package is $6,772,090.
-
MAY 21, 2021
Bid Package 004.SC.03 Demolition & Disposal of Existing Mooring Dolphins is awarded to Blakeslee Arpaia Chapman Inc. of Branford, CT. The contracted price for this package is $2,121,338.
-
MAY 6, 2021
Bid Package 014.SC.08 Support Services - Bull Gang is awarded to Kiewit Infrastructure Co. of Woodcliff Lake, NJ. The contracted price for this package is $2,328,852.
-
MAY 6, 2021
Bid Package 002.SC.01 Security Guard is awarded to USA Security Services Corp. of Newington, CT. The contracted price for this package is $1,173,211.
-
MAY 6, 2021
Bid Package 003.SC.02 Dredging is awarded to Cashman Dredging & Marine Contracting of Quincy, MA. The contracted price for this package is $150,000.
-
APRIL 22, 2021
Bid Package 013.IWO.04 Construction Photographs is awarded to GM2 Associates of Glastonbury, CT. The contracted price for this package is $17,798.
-
APRIL 22, 2021
Bid Package 011.SC.07 Site Survey is awarded to RCL Thompson, LLC of Clinton, CT. The contracted price for this package is $29,380.
-
APRIL 22, 2021
Bid Package 010.SC.06 Building Demolition is awarded to Stamford Wrecking Co. of Trumbell, CT. The contracted price for this package is $326,570.
-
APRIL 22, 2021
Bid Package 021.SC.09 Bridge Demolition is awarded to Stamford Wrecking Co. of Trumbell, CT. The contracted price for this package is $204,451.
-
APRIL 21, 2021
Bid Package 023.IWO.03 Bathroom (Temporary) Plumbing Hook-Up is awarded to Ed Bartelli, Inc. of Waterford, CT. The contracted price for this package is $50,461.
-
APRIL 21, 2021
Bid Package 008.SC.05 Erosion and Sediment Control is awarded to Loureiro Contractors of Planville, CT. The contracted price for this package is $307,643.
-
APRIL 21, 2021
Bid Package 005.IWO.01 Electrical (Temporary) Trailer Hook-Up is awarded to Anderson Electrical of Hartford, CT. The contracted price for this package is $31,866.
-
APRIL 21, 2021
Bid Package 001.MC.01 Supply of Permanent Pile is awarded to JD Fields of Mersin, Turkey. The contracted price for this package is $18,563,292.
-
March 30, 2021
Evidentiary Hearing portion of the CTDEEP Public Hearing is held
-
March 23, 2021
Public Comment Session portion of the CTDEEP Public Hearing is held
-
February 12, 2021
CTDOT commences on-site remediation
-
DECEMBER 21, 2020
Final Remedial Action Plan (RAP) is submitted to CTDEEP
-
DECEMBER 18, 2020
Kiewit Infrastructure Co. is selected as the Construction Manager At-Risk
-
DECEMBER 16, 2020
CTDEEP Public Notice is released
-
October 30, 2020
Revised JPA (Revision 2) is submitted to CTDEEP and USACE documenting revised dredge footprints
-
October 21, 2020
90% Design Documents are submitted
-
October 7, 2020
Phase III Environmental Site Assessment is completed
-
September 22, 2020
Request for Proposal (RFP) for a CMR firm is released
-
August 4, 2020
USACE Public Notice is released
-
July 28, 2020
60% Design Documents are submitted
-
July 21, 2020
Request for Qualifications (RFQ) for a Construction Manager At-Risk (CMR) firm is released
-
June 1, 2020
30% Design Documents are submitted
-
May 8, 2020
Revised JPA (Revision 1) is submitted to CTDEEP and USACE documenting revised Installation Vessel berthing configuration
-
April 27, 2020
AECOM is conditionally selected as the Construction Administrator
-
April 7, 2020
Construction Stormwater General Permit authorization is issued by CTDEEP
-
January 9, 2020
Construction Stormwater General Permit application submitted to CTDEEP
-
November 1, 2019
USACE issues CT GP Authorization under GP 2
-
October 7, 2019
CTDEEP issues Certificate of Permission (COP)
-
September 11, 2019
Application for Certificate of Permission (COP) and Connecticut General Permit (CT GP) authorization are submitted for select Phase 1 activities (oversheeting the Northeast Bulkhead, demolition of the Mooring Dolphins, Northeast Annex and related activities)
-
May 6, 2019
Joint Permit Application (JPA) is submitted to Connecticut Dept. of Energy & Environmental Protection (CTDEEP) and U.S. Army Corps of Engineers (USACE)